KHARIR CCU Extension - Additional Separator and Production Facilities Project.

CLIENT : TOTAL E&P Yemen

Picture5.jpg

Scope of work:

  • Booster compressor -22MMSCFD 25 Barg

  • Oil booster pumps – 5 with 2400& 4500 blpd 17 barg

  • Fuel Gas treatment package – 0.45 MMSCFD

  • Separator 100,000 blpd /-1

  • Fire water tank-2, fire water pumps -1

  • Fire water net works, fire hydrant, fire hydrant monitors

  • 6.6 kv switchboard & 6.6 kv transformers

  • Installation of 400V MCC and connection of all equipment to this MCC

  • Update of the control ESD, F&G systems in  new Technical building

  • 5km 12” pipe line with pig launcher & pig receivers

JAMEEL AHAMED